[단독] The Yeouido dock, which was completed in February, is said to be still under construction.

◀ Anchor ▶

Last year, the city of Seoul announced that it will spend about 30 billion won to build a dock with various convenience facilities on the Han River near Yeouinaru Station, and even end the selection of private business.

However, even now, well past the scheduled completion date of February this year, the building frame has not even been built.

Reporter Lee Ji-eun covered the incident first.

◀ Statement ▶

This is the Yeouido dock, which was scheduled to be completed in February this year.

A three-story building containing restaurants and convenience stores will be built on top of a 102-meter-wide, 34-meter-long boat, the size of half a football field, floating on the river and two boats can 200-ton dock trips at the same time.

The estimated construction cost is around 30 billion won, and the city of Seoul completed the selection of a private operator last March.

However, now, eight months after the scheduled completion date, the dock is still under construction.

The construction sign does not even indicate the construction start date or expected completion date.

[현장소장(음성변조)]

“At the time of production, we didn’t have a clear schedule…”

The boat that would be the base for the three-story building hadn’t even arrived on site due to design changes.

[현장소장(음성변조)]

“As you can see, there is no (ship), so shouldn’t a ship come in to do it in addition to this (ship)?”

It turned out that the company asked to extend the construction period five times, delaying its completion until December of this year.

However, although the construction was delayed, there were only two reminders from Seoul City through official documents.

In response to this, the Seoul Metropolitan Government explained that they had made a phone call and did not think it would be difficult to conduct normal business.

They also said they would complete it by December.

However, construction companies are concerned about safety.

[현장소장(음성변조)]

“We can do it if we do it quickly take that long to do it on land. “…

I went to the address on the record of the company that won the business license, but it was a shared office, and I could not meet any company officials there.

This is Lee Ji-eun from MBC News.

Video broadcasting: Won-seok Lee / Video editing: Yun-seon Ahn / 3D design: Jeong-un Song

MBC News awaits your reports 24 hours a day.

▷ Phone 02-784-4000
▷ Email mbcjebo@mbc.co.kr
▷ Kakao Talk @mbc report

2024-10-14 11:24:00
#단독 #Yeouido #dock #completed #February #construction

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.