NCCC Yasothon inspects reinforced concrete road projects Connecting between Don Khueng village – Ban Lang Phan is separated into 2 projects made from the source but the end does not converge, disappearing for more than 100 meters.
—
On February 10, 64, Mr. Adul Wandee, director of the Office of the National Anti-Corruption Commission (NACC), Yasothon Province, revealed that he, along with the Strong, Sufficiency, Anti-Corruption Club. Traveled to inspect the reinforced concrete construction project of Lumpuk Subdistrict Administrative Organization Kham Khuean Kaeo District, Yasothon Province, which connects Don Khueng Village – Ban Lang Pan, Lumpuk Subdistrict, Kham Khuean Kaeo District, Yasothon Province After a complaint has been made that the aforementioned reinforced concrete road, Lum Phuk Subdistrict Administrative Organization has split into 2 projects, both of which are the same road. But after the construction was completed, the two concrete roads were disconnected by missing almost 100 meters, the villagers who saw them were surprised as to why the construction was not completed.
—
Featured News
–
Mr. Adul continued that from the investigation, it was found that the construction of such concrete roads, Lumpuk Subdistrict Administrative Organization, had actually made two projects, with Project 1 being a road construction project. Kor Sor. Local highway code Yor Sor Tor 70-221 size, width 4 meters, distance 2,900 meters, thickness 0.15 meters, connecting between Ban Don Khueng Village, Village No. 8- Ban Lang Paen, Village No. 10, Lumpuk Sub-district, Kham Khuean Kaeo District, Yasothon Province Budget 9,655,000 baht The contract starts on 29 May 2020, expires on 25 October 2020 and the second project is a road construction project. Kor Sor. Local highway code Yor Tor 70-309, connecting between Ban Lang Phaen, Village No. 10- Ban Don Khueng, Village No. 8, size 4 meters wide, 1,580 meters long, 0.15 meters thick, budget 3,660,000 baht. Jan. 2020 and the contract expires on 25 October 2020
—
–
NCCC Director of Yasothon said that the two concrete roads were made in the same road, but the starting point of the project was on the other side when the construction was completed, thus causing the two roads to be disconnected. To the surprise of the witnesses, the end of the non-converging road is in the middle of a rice field for a distance of almost 100 meters and after this he will ask to re-examine the project details and the procurement process that has been Proceed according to regulations Is the law correct or not?
Mr. Wasan Chaiyaphum, President of Lumpuk Subdistrict Administrative Organization, clarified that the aforementioned project was the project. That has been allocated budget subsidized by the Department of Local Administration at Lumpuk Subdistrict Administrative Organization has requested the budget to enter, both of which have different distances, with the 1st project starting from Ban Don Khueng, Village No. 8 to the house Sources of Pan, Village No. 10, the 2nd project starts from Ban Ban Phanen, Village No. 10 to Ban Don Khueng Village, Village No. 8, which must be separated into 2 projects because the Department of Local Administration has determined Each project must not exceed 10 million, which the said road. Single budget will exceed 10 million baht, so it is necessary to split into 2 projects.
The Prime Minister of the Lumpuk Subdistrict Administrative Organization said that the reasons for the two roads of the project were not connected due to the limitation of the timing. Urgent expedition to explore and design And was designed to allow these two projects to not overlap Thus causing an error in measuring the distance Because there are many curves along the way As a result, the remaining distance was one period. Initially, the SAO knew that the roads were not connected Therefore, it was prepared to improve by requesting a budget from the Lumphuk Subdistrict Administrative Organization to proceed with the construction to connect as soon as possible.
—