A very high voltage electricity network transmission project will cross Bagneux, mainly via rue des Meuniers until August 2024. The work program…

The creation of many public transport lines (Grand Paris Express lines, electrification of buses, etc.) but also the economic development of the region, generate significant electrical needs. This requires strengthening the supply between the transformers of Arcueil and Clamart, with the installation of a very high voltage network extending over 2,250 linear meters in the territory of Bagneux.

The RTE project (Electrical Transport Authority) consists of passing very high voltage power lines through the city, which arrive from Clamart via rue Blanchard to the Bertholet substation located in Arcueil.

This operation, which will last until August 2024, will take the streets Blanchard, Jean-Baptiste-Fortin, Froide, Gabriel-Péri and des Meuniers. It will also cut off the RD920.

It consists of passing cables suitable for very high voltage, as well as a sheath for the telecommunications cables in a concrete block, buried 1.5 meters above the ground.

The work will be carried out in sections of 150 meters in length so as not to obstruct traffic too much. The track will be opened, the sheaths put in place, then the asphalt will be redone before moving on to the next section.

During the works, traffic will be on one lane. Diversions may be put in place.

Planning of the 1st phase of the works

From April 17 to May 12, 2023 – Rue des Meuniers (between avenue Gabriel Péri and rue Marc Sangnier): right of way and sidewalks

  • Vehicle traffic prohibited in the direction of avenue Gabriel Péri and rue Marc Sangnier
  • Vehicle circulation will take place on a lane of at least 3m in the uphill direction
  • Diversion put in place via avenue Henri Barbusse, rue Jean Longuet, avenue Louis Pasteur,
  • Resident access maintained
  • Pedestrian traffic maintained
  • Maximum speed limited to 30km/h
  • Parking prohibited at the intervention sites.

From April 17 to August 4, 2023 – Rue des Meuniers (between rue Marc Sangnier and avenue Louis Pasteur): right of way and sidewalks

  • Vehicle traffic prohibited in the direction of rue Marc Sangnier, avenue Louis Pasteur
  • Vehicle traffic will be in the uphill direction
  • Diversion put in place
    * 1° avenue Henri Barbusse, avenue Louis Pasteur, rue des Meuniers, rue Hardenberg
    * 2° rue Hardenberg, avenue Albert Petit, avenue Louis Pasteur Access for local residents will be maintained at all times
  • Pedestrian traffic maintained
  • Maximum speed limited to 30km/h
  • Parking prohibited at the intervention sites.

Further work…

From August to November 2023 : rue des Meuniers (from avenue Pasteur to the RD920)

From November 2023 to August 2024 : Rue des Meunier, (from rue Engehart but going up this time), avenue Gabriel-Péri, rue Froide, Avenue Jean-Baptiste-Fortin, rue Blanchard

July 2024 : the part of avenue Gabriel-Péri in front of the Rosenberg school will be carried out in July 2024 so as not to interfere with school operations.

#Bagneux #high #voltage