In just two weeks, the construction of a new gas power plant, owned by Polska Grupa Energetyczna, Dolna Odra near Szczecin, is to be completed. There are questions about whether it will be successful.
PGE officially informs that it is in constant contact with the contractor, who will ensure that the works will be completed on time. Unofficially, however, the company has great doubts. The company is already paying fines for failing to complete the investment on time and connect it to the National Power System, in accordance with the capacity market contract with Polskie Sieci Elektroenergetyczne.