Todtnau: From June 8th: Badenova renews the gas pipeline in Todtnau – Badenova subsidiary bnNETZE invests in local infrastructure

The regional energy and environmental service provider badenova is investing in the natural gas infrastructure in Todtnau: To this end, the subsidiary bnNETZE will be renewing parts of the natural gas pipelines in Carl-Otto-Keller-Strasse from around June 8th. The work is carried out by the Asal company from Todtnau.

The construction work will take place in the intersection of Fridolin-Wißler-Straße 2 up to Carl-Otto-Keller-Straße 11. In the course of the work there are half-sided road closures as well as partial obstructions for the approach roads.

The affected residents will be informed in good time about the short-term restrictions on access to the property.

The measure takes place in calendar week 24. The construction work should be completed by the end of August 2020.

The bnNETZE renews the old cast pipes from 1964 over a length of 230 meters. In the course of the construction work, four supply lines will be replaced by modern plastic lines and the water, power lines and broadband cable will also be installed.

Traffic can be impaired during the day during construction. BnNETZE asks for your understanding.