The Gulf to Provide Power to EGAT: Second Production Unit, with Clear Investments, Set to Begin Commercial Operation at 662.5 MW – Stock Specifications.


Stock dimension – Gulf Energy Development Public Company Limited or GULF Informed the SET that Gulf PD Company Limited (GULF’s subsidiary) is the operator of the Gulf PD power plant project or GPD power plant that has been commercially operated. Installed 662.5 megawatts (MW) by supplying electricity to the Electricity Generating Authority of Thailand (EGAT) system with a contract period of 25 years.

The GPD power plant project, located in Rojana Industrial Park (Pluak Daeng), Pluak Daeng District, Rayong Province, is one of the group of IPP power plants under “Independent Power Development Co., Ltd.” or IPD. ” which operates 2 IPP projects with a total installed capacity of 5,300 MW, namely GSRC power project and GPD power project, with an installed capacity of 2,650 MW each (divided into 4 production units, 662.5 MW each )

All 4 units of GSRC power plant have already been commercially operated. Between the years 64-65 As for the GPD power plant project, the second production unit is scheduled to start commercial operation in October 2023 and the third production unit in March 2024. and production unit 4 in October ’24

Follow the stock dimension channel to receive capital market news via the link below.

Web :

Facebook :

Youtube :

Tiktok : www.tiktok.com/

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.