At the last minute it is reported that a rod structure collapsed on line 6 of the Monterrey Metro, Nuevo León, which was part of some columns; Fortunately, the workers who were on the job were not injured. At AS México we tell you what happened.
Structure of line 6 of the Monterrey Metro collapses
This afternoon, Tuesday, April 9, while workers were working on line 6 of the Monterrey Metro, they witnessed a huge column of rods collapse; The event took place on Prolongación Madero Avenue, right in front of the “Y Griega” Metro station.
YOU MAY BE INTERESTED: Peru requests a visa for Mexicans 2024: how to do the process and what are the requirements?
Emergency and security elements arrived at the scene, who confirmed that the structure collapsed on the opposite side to where the workers were. Some cranes also arrived in the area to help remove the heavy structure, a situation that according to local media lasted almost two hours.
YOU CAN ALSO READ: How to download the SAT Tax Status Certificate online this 2024?
The authorities of Monterrey and the Metro have not issued any statement regarding the incident recorded this afternoon. So far the construction of lines 4 and 6 is 20% complete, while line 5 is expected to be ready by the end of 2024. The authorities’ balance sheet highlights that so far there is:
- 290 batteries made
- 110 shoes
- 90 columns
- 64 capitals
- 40 girders placed
Related news
The Infrastructure Secretariat expects that in 2026, the lines under construction will operate at 100%. “In this way we ensure that by the month of June 2026, we will arrive with the Metro in operation, at least from the Airport to the Gynecology station,” said the head of the department, José Francisco Ibargüengoytia.
Follow the Diario AS channel on WhatsAppwhere you will find all the sport in a single space: the current news of the day, the agenda with the latest news of the most important sporting events, the most outstanding images, the opinion of the best AS brands, reports, videos, and some humor from time to time.