Mr. Prapas Kong-iad, Director-General of the State Enterprise Policy Office (Sor Kor Sor), revealed that the disbursement results as of November 2020, 44 state enterprises that are regulated by SEPO can disburs the investment budget in 2020 in the amount of 215,205. Million baht or 80 percent of the cumulative disbursement plan consisting of
Disbursement of investment budget for state enterprises in the fiscal year system (From October 2019 – September 2020) 34 places with disbursement actually amount 100,783 million baht and state enterprises in the calendar year system (From January to December 2020), 11 locations had actual disbursements of 114,422 million baht, which is expected that the disbursement of the investment budget for the year 2020 will be approximately 256,257 million baht or 83% of the full-year investment framework. This is higher than the investment disbursement rate in 2019, which was 78 percent of the full-year investment framework. And excluding 4 projects with continuous delay in disbursement, namely, the Thai-Chinese high-speed rail project, Phase 1 (Bangkok-Nakhon Ratchasima section), the rail mass transit system in the Bangkok Metropolitan Area and the Red Line, the Airport Development Project Suvarnabhumi (Fiscal Year 2011 – 2017) and the Rama 3 – Dao Khanong – Western Outer Ring Road Expressway Project There will be a 96 percent annual disbursement on investment, which is more than 95 percent higher than the Cabinet’s target for disbursement.
Cumulative disbursement result of state enterprises for the year 2020 to November 2020
(October 2019 – November 2020)
State enterprises actual disbursement accumulated
(Million Baht) Accumulated Actual Disbursement Percentage /
Accumulated disbursement plan
Fiscal Year (Oct. 19 – Sep. 20)
34 locations (the operation ended) 100,78367%
Calendar year (Jan. 2020 – Dec. 20)
10 locations (11 months) 114,42298%
Total 44 places 215,20580%
Ms. Piyawan Lamkitcha, State Enterprise Development Advisor It added that in 2020 there are large investment projects that can be disbursed according to the plan, such as the improvement of the power transmission system in the western and southern regions to strengthen stability Improvement of power transmission system in the lower South. To strengthen the power system Of the Electricity Generating Authority of Thailand Transmission and Distribution System Development Project Phase 1 of the Provincial Electricity Authority The MRT Green Line Project, Mo Chit – Saphan Mai – Khu Khot Section of the Mass Rapid Transit Authority of Thailand (MRTA), the Electric Power Distribution System Improvement and Expansion Plan, Issue 12, 2017 – 2021 of the Metropolitan Electricity Authority And the long-term plan for the natural gas business of PTT Public Company Limited
For state enterprises’ investment disbursement in 2021, at the end of November 2020 of state enterprises for the fiscal year, there was a 2-month cumulative disbursement result (November 2020) of 52,267 million baht, or 102% of the investment disbursement plan. The large investment projects that can be disbursed better than the target are the Orange Line Metro Project. The Cultural Center – Minburi of the MRTA, the construction of the double-track railway in Nakhon Pathom – Chumphon and the Thai-Chinese high-speed rail project Phase 1 (Bangkok-Nakhon Ratchasima section) of the State Railway of Thailand.
State enterprise disbursement results for the year 2021 to November 2020
State Enterprises Disbursement Actual Accumulated% Accumulated Actual Disbursement /
Accumulated disbursement plan
Fiscal Year (Oct. 20 – Sep. 64)
34 locations (2 months) 52,267 102%
Calendar year (Jan.
10 locations (start operation Jan. 64) –
Total 44 places 52,267 102%
Mr. Prapas Kong-ied, Director of Sor Kor Por Sor, concluded that on December 23, 2020, the Ministry of Finance held a meeting of the committee to monitor budget disbursement and government spending. With the Minister of Finance as the president To monitor and expedite public spending Budget disbursement for budget receiving units Including large infrastructure investment projects Most of the disbursement of the government sector in 2021 was in line with the target. The investment of state-owned enterprises is considered an important part of the government’s investment expenditures, Sor Kor Sor Sor Kor., Therefore, requests cooperation with all state enterprises to monitor the disbursement of investment budgets, especially large-scale investment projects. Make state-owned enterprises a faster front-loaded disbursement plan by accelerating disbursement of investment budgets in the first quarter of 2021 so that the disbursement of state-owned enterprises is a mechanism to help stimulate economic growth continuously in the year 2564
– .