Sibiu-Piteşti Highway: The builder has been designated for the 31 kilometers. When it should be ready

“With a length of 31.33 km, the duration of its design and execution is 5 years and 6 months,” the minister said.

According to him, the contract is financed from European non-reimbursable funds, the main data being the following:

– Section 1 (Sibiu – Boiţa) of 13.17 km is in the execution phase.

– Deadline: 2023.

– Section 3 (Cornetu – Tigveni) of 37.4 km is in the tender phase for the design and execution contract.

– Opening of tenders: January 2022.

– Section 4 (Tigveni – Curtea de Argeş) of 9.86 km is in the design phase.

– Deadline: 2025.

Section 5 (Curtea de Argeş – Piteşti) of 30.35 km, is under construction.

– The deadline is 2025.

CNAIR subsequently announced the winner – the association of Turkish companies Mapa Insaat Ve Ticaret AS – Cengiz Insaat Sanayi Ve Ticaret AS – and the value of the contract.

“On Thursday, 30.12.2021, following the completion of the tender evaluation process, CNAIR communicated the result of the contract award procedure for the design and execution of section 2 of the Sibiu – Pitesti, Boiţa – Cornetu Highway. The winning bidder is the association Mapa Insaat Ve Ticaret AS – Cengiz Insaat Sanayi Ve Ticaret AS, with the price of 4,250,006,315.00 lei without VAT “, announces CNAIR.