Reopening of Notre-Dame de Paris: where is the construction site less than 100 days from reopening?

Less than 100 days before the reopening of the cathedral, which is scheduled for December 8, 2024, the challenge of rebuilding Notre-Dame de Paris will be met in 5 years.

Less than 100 days from reopening Notre Dame Cathedral in Pariswhere are we with the cathedral restoration project? Despite the presence of trees and scaffolding that can still be seen, the cathedral is on its way to regaining its beauty. In addition to the fully renovated roof, the Viollet-le-Duc steeple, which collapsed due to a fire​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​15th April 15, 2019, the steeple of the Viollet-le-Duc will end up, partially covered, at 96 meters in the sky. Paris. At the end of a major renovation project, the largest in Europe, Notre Dame de Paris is revealed because we have never seen him since December 8th.


Most of the work

« We are on schedule, and at this point most of the work is behind us » says, at the BFMTV microphone, Philippe Jost, President of the public institution Rebâtir Notre-Dame de Paris, who is in charge of the renovation project. After acquiring the cathedral between 2019 and 2021, the restoration project began with a complete restoration of the interior, which is now complete, the closing of the fallen vaults, giving a- crossing in May of this year, and restoration of the exterior: reconstruction of the missing oak. frames and spire Viollet-le-Duca true masterpiece of carpentry, reconstruction of the north and south arches which were in danger of falling, restoration of the north bell…

Surprised for the reopening

The great surprise of the reopening will undoubtedly be the rediscovery of the interior of the building. cathedralcompletely cleaned and restored. We remember the state of advanced dirt the building was in before the fire. As a result of the work, it has regained the freshness of its stone, the light of its stained glass windows and the clear bright colors of the choir chapels painted at the end of the 19th century.

The latest works

Between now and December 8, there are still a few tasks to be completed: the repair of the floor tiles, the end of the electrical work, but also the installation of the bells of the north bell, the end of the construction of the liturgical plateau and the installation of the furniture, in charge of the artist Guillaume Bardet. Finally, the reopening of Notre-Dame will not mark the end of the work: thanks to the extraordinary generosity of donors, 140 million euros, out of the 846 million collected during the sub- of national writing, are still available and will be used by the public. set up to continue working on the external elevations, reinforcing the flying buttresses and restoring the exterior of the Viollet-le-Duc sacristy. They will be done at the same time as the work done by the City of Paris to reclassify the monument’s surroundings.

At its peak, the scaffolding was up to 100 meters high. © Rebuilding Notre-Dame

Manage the income of visitors

Visited by 12 million people a year before the fire, the cathedral should welcome 15 million when it reopens. Waiting times for admission will therefore be extended. So the diocese of Paris has set up a ticketing system, which should open in the autumn, making it possible to book a visiting slot​​​​a few days in advance, in the hope of streamlining the visiting route which has been re – completely designed.