As of: October 1, 2024 12:47 p.m
The reconstruction of the Jungfernstieg is entering its final phase: According to the Hamburg Senate, the asphalting and marking work has now been completed.
According to the transport authority, the Jungfernstieg is now open to buses, taxis, cyclists and delivery traffic in both directions. However, the Jungfernstieg remains taboo for private car traffic. The next step is to renew the sidewalks. They will be paved and new benches will be installed. There are also new bollards, trash cans and flower pots.
Construction work is on hold due to the Christmas business
There will be a break in construction from the end of November to the beginning of January. The reason: consideration for the Christmas business and the “Winterzauber” Christmas market on the Alster. When the renovation is finished, the Jungfernstieg should be safer and more attractive. There will be more space for pedestrians and cyclists.
Redesign is scheduled to be completed in May 2025
The redesign is scheduled to be completed at the end of May 2025. The city of Hamburg is investing a total of 13.4 million euros in the project.