Home » News » Main Franconia: New roads for the counties

Main Franconia: New roads for the counties

New roads for the district – this year they are in Würzburg, Kitzingen and Main-Spessart. As the State Building Authority informed the editors when asked, major road projects are planned for this year in all three districts mentioned.

Three upcoming construction sites stand out because they will affect a particularly large number of drivers. This is the last phase of construction in the Marktheidenfeld through-road on the B8, where there will probably be a complete closure from the second half of the year until spring 2024.

The renewal of the roadway on the B27 between Thüngersheim and Veitshöchheim will also require a lot of patience. As well as the conversion of the “Am Traugraben” crossing in the Kitzingen district and the renewal of the road surface near Marktsteft. Here, too, there will be a complete closure in two sections – probably from May.

Here is a list of the planned measures:

District of Würzburg:

B27, renewal of the roadway between Thüngersheim and Veitshöchheim

WÜ57, expansion between Untereisenheim and Obereisenheim

WÜ11, expansion between Neubrunn and the district border

St2260, renewal of the road surface west of Prosselsheim

St2269, renewal of road surface south-west of Aufstetten

District of Main-Spessart:

St 2299, renovation of the Billingshausen through road, diversion has been set up, full closure continues

St 2294, renewal of the road surface between Arnstein and Gramschatz, complete closure expected in the first half of the year

St 2302, renewal of the road surface south of Wolfsmünster, complete closure expected in the first half of the year

B 8, last construction phase in the Marktheidenfeld through road, full closure expected from the second half of the year until spring 2024

B 276, renewal of the road surface north of Frammersbach, complete closure expected in summer

Bypass Hafenlohr, St 2315 Construction of the southern junction (local connection), the state road is expected to be completely closed for several weeks in the second half of the year

District of Kitzingen:

B 8, renewal of the road surface in the OD Kitzingen, 3rd construction phase, probably summer holidays

St 2271, conversion of the “Am Traugraben” crossing and renewal of the road surface near Marktsteft, full closure in 2 sections, probably from May

St 2272, expansion east of Kitzingen (between Kitzingen and Großlangheim), complete closure, expected autumn 2023

St 2260, renewal of the roadway east of Geiselwind, 3rd construction phase, complete closure, expected spring 2023

St 2258, renewal of the road surface near Füttersee, complete closure, expected spring 2023

St 2257, renewal of the road surface near Haag, complete closure, expected spring 2023

St 2418, renewal of the road surface between Obernbreit and Iffigheim, full closure, probably in the second half of the year

St 2418, renewal of the road surface between Nenzenheim and Dornheim, complete closure, probably in the second half of the year

In addition, measure B 22, renewal of the OD Düllstadt, has been running since last year and should be completed this year