The southern section of the line 1 of Madrid’s Underground closes this summer for construction. From the June 24 the service that goes from valdecarros until Sol It will not be available on this tour, a situation that will last for four months.
From the newspaper ‘La Razón’ it has been specified that the cut will last until 4th of Septemberbut the company would have moved the works council a more open interruption fork.
During this time, the first phase of works. Already in 2024 will continue with the second, as confirmed by union sources to Europa Press. Actually the previous performances began in Marchbut it was unknown when it would continue.
After this announcement, Atocha will live a summer isolated of the suburban network. It is added to the difficulties that the Cercanías Madrid service is undergoing for the construction that you are developing.
Although in summer the drop of users to carry out performances in the Metro, coincides with the arrival of tourists to the capital, part of them nationals and arrived precisely by the old Midday Station.
What will the renovation works on Line 1 be like?
From the Madrid’s community They have explained that the works will make it possible to comprehensively improve the functioning of Line 1, which will mean reducing the travel times of trains and offer greater benefits technological.
Those that increase the reliability of the facilities and optimize the work and maintenance costs track, among other benefits. The project consists of removing the ballast (the traditional piedras that can be seen in some sections of the track).
will also be removed wooden sleepers existing ones to replace them with a new rail track platform. concrete. Thus renewing the systems of support and support of the rail, as well as installing new devices that manage the crossing or branching of roads.
From the beginning, the regional executive informed that a service substitute for buses of the Municipal Transport Company of Madrid (EMT), but from the opposition they have criticized that not be profiled.
Expanding Metro Line 11 is being considered
It is left like this for more than 120 days no Metro service to the districts of Bridge and Villa de Vallecas, which are vertebrated by this line. These same sources have indicated to Europa Press that it would also be shuffling take advantage of this cut for the enlargement from line 11 from Metro to Atocha.
This line is stop for a few months after the neighborhood pressure. The plan contemplates the construction of a station in the Comillas Park and in Madrid Río. These new infrastructures would mean the story of more than a thousand treeswho took the neighbors to the streets to avoid it.