Installing an Electricity Meter in Saudi Arabia: Steps, Requirements, and Fees

One of the most prominent services provided by the Saudi Electricity Company is the service of connecting electrical current and ensuring that electricity reaches all commercial stores, as well as residential units. When an individual moves to a new home or office, he needs to install a new electricity meter, as the company is working to develop these meters. continuously.

How to install an electricity meter in Saudi Arabia

Individuals can obtain an electricity meter through the following steps:

Read also:The largest economic event The Kingdom announces hosting the World Economic Forum meeting soon.. The most famous coffee and sweets in the Kingdom of Saudi Arabia The 5 cheapest cars you can buy in the Emirates with surprising prices, specifications and great benefits 2024 What are the cases of dropping the name from the citizen’s account? How to submit an objection? How to monitor students’ grades using the Noor 1445 system

  • Enter the electricity company platform from here Link

  • From the home page, click on the phrase “Log in”.

  • Write your email and password in the appropriate place.

  • Click “Sign in”.

  • Click on the services menu.

  • Click on “Subscriber Services”.

  • Click on the Request to Install an Electric Meter tab.

  • Choose to install a new electricity meter.

  • Enter the data that the site requests from you.

  • Click “Send Request”.

Conditions and requirements for installing electricity meters in the Kingdom

The Ministry of Electricity has set several necessary conditions that must be met in order for individuals to be able to install the meter. These conditions are:

  • If the coordination certificate is not obtained, a copy of the building permit must be brought.

  • Bring a coordination certificate, which is a certificate extracted from the company.

  • The presence of buildings without sound, and he must bring a letter of approval from the Ministry of Housing.

  • Thermal insulation must be applied, according to the electricity company’s regulations.

  • Availability of security and safety conditions in the place where electricity will be connected.

  • The location of the meters must be equipped according to what the company specified, in addition to the cable sizes.

  • Requests for electrical current delivery and installation of meters must be received from the Modon platform for industrial buildings.

  • The coordination certificate must contain the amount of the building loads, the capacity of the breakers, the location of the meters, the number of units, in addition to the dimensions and size of the cables.

  • If the facilities are not affiliated with the Industrial Estates and Technology Zones Authority, in this case the application must be submitted at the company branch and a copy of the building permit and the Ministry of Industry license must be brought, as well as an energy efficiency certificate.

What are the fees for electricity meters in the Kingdom?

The electricity company provides a group of meters with different operating and load capacities. These meters vary in price depending on the hour and voltage, and they are as follows:

  • The cost of a meter with a capacity of 200 amps and a voltage of 76.2 volts is 11,430 riyals.

  • The cost of a meter with a capacity of 100 amps and a voltage of 69 volts is 10,350 riyals.

  • The price of a meter with a capacity of 100 amps and a voltage of 38.1 volts is 3620 riyals.

  • The cost of a meter with a capacity of 70 amps and a voltage of 26.67 volts is 1,600 riyals.

  • Finally, the cost of the meter with a capacity of 70 amps and a voltage of 48.3 volts is 4589 riyals.

Steps to inquire about electricity meter installation fees

Individuals can find out the fees for installing the meter electronically through the official website of the electricity company through the following steps:

  • Enter the electricity company platform from here Link

  • Choose the induction service and receipt fee.

  • From the list of services, click on the “My Account” service.

  • Then click on the voltage available from the service.

  • Choose the type of activity: Commercial, Residential, or Service Meter.

  • Write the required data for the units.

  • Click on “Account vs Receipt”.

  • Then the cost you want to know will appear in front of you.

Read also

2024-01-20 12:55:01
#steps #installing #electricity #meter #Saudi #Arabia #important #conditions

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.