The construction of the Fougères gymnastics hall ended in December 2020 with two years delay (© Archives Chronique Républicaine).
As part of the construction of the gymnastics hall, delivered at the end of last December with two years delay, the City of Fougères had entrusted the contract for lot n ° 2 (special foundations, structural work) to the Heude Bâtiment company.
During the municipal council, Thursday 28 January, Diana Lefeuvre, 2e assistant for ecological and energy transition and works, presented:
“As a result of the findings made by the project manager, the City had to notify the company, by letter dated November 20, 2020, of provisional late penalties of € 29,122.32 for work situation no. 6 and provisional deductions of € 13,000 on work situation no. 9 ”.
Heude Bâtiment presented a complaint, received at the town hall Thursday November 26, 2020.
“Given the relevance of the arguments developed and the involvement of the company in the amicable resolution of this suspended case”, continues Diana Lefeuvre, it was proposed to the municipal council to pronounce a total exemption, to with regard to the company, penalties for delay in the situations exposed, ie € 42,122.32. The elected officials voted unanimously for this deliberation.
Thursday December 10, 2020, the municipal council of Fougères had decided to penalize the Sotrav company (€ 11,200) for significant delays on a renovation site for wastewater pipes on rue Marceau.
.
–