Financial monitoring board 64 To acknowledge the progress of 105 Mecca government projects amounted to 2.56 trillion after adding 9 large investment projects. Found disbursement of more than 7.9 billion, 83 self-employed government projects worth 2.04 trillion baht, 30 contracts have been signed, worth 7 hundred billion.
Today (3 Mar), a report from the Ministry of Finance revealed that on March 4, the Ministry of Finance. Prepare to hold a meeting of the committee to expedite budget disbursement and government expenditures no.1 / 2021, in which the agenda is to report on the progress of investment in large projects worth 1,000 million baht or more of all government agencies and state enterprise Especially investment expenditures with a credit limit of more than 1,000 million baht
Recently, it was found that large projects valued at 1,000 million baht or more in fiscal year 2021 there were more than 105 projects, total project value of more than 2.56 trillion baht, and there were additional reports of 9 large investment projects. Pay 1.9 billion baht, disbursed over 7.9 billion baht
“It was found that 83 state-run projects worth 2.04 trillion baht, 30 of which have been signed, worth 7 hundred billion baht. 53 projects that have not yet been signed, worth 1.33 trillion baht, which are in the process of procurement and disbursement according to the work period, in which there are projects that are likely to have problems with disbursement of 16 projects worth 5.3 hundred billion baht, fraction Which is the investment value in 2021 in the amount of 6.7 billion baht, fraction “
In addition, there are 22 projects of joint public-private investment (PPP), 2 projects worth 1.1 billion baht, 20 unnamed projects worth 4.1 billion baht.
In the meeting tomorrow (March 4) it is expected that the progress of the project will be reported in excess of 1 billion. 9. Additional large new investment projects are the high-speed rail project connecting the 3 airports of the State Railway of Thailand. Thailand, worth 3.5 billion baht, Suvarnabhumi Airport Development Project, Phase 2, worth 6.2 billion baht, Runway Development Project, Phase 3 of Airports of Thailand Public Company Limited, worth 2.1 billion baht.
A 1.8 billion baht smart meter system (AMI) installation project for large electric power users, a submarine cable construction project to Koh Tao. Surat Thani Province, worth 1.8 billion baht, the transmission and distribution system, phase 2, worth 7.7 billion baht of the Provincial Electricity Authority And a broadband service plan project of a telecommunications company (public company limited) worth 1.1 billion baht
While it is a PPP project, it is the Phuket Mass Transit System Project, Phase 1, International Airport Section. Phuket – Chalong Intersection Of the Mass Rapid Transit Authority of Thailand worth 35 billion baht and the development and management of roadside accommodation on the highway between the city of Bangkok – Ban Chang, Chonburi – Pattaya (Sriracha district) of the Department of Highways worth 1.7 billion baht .
– .