Original title: Fangshan completed the restoration and reconstruction of 34 flood-damaged roads

Laibao Road, the main road in Shidu Town, is under intensive repair.Photo by our reporter Pan Zhiwang

Report from our newspaper (Reporter Sun Hongyang) During the heaviest rainfall this summer, 54 roads including National Highway 108 in Fangshan District were damaged to varying degrees. So far, the highway department has completed the restoration and reconstruction of 34 roads including Dongfang Road, and the remaining projects are scheduled to be completed by the end of May next year. At the same time, Fangshan District is conducting preliminary research and design on the 108 New Line Expressway and Laibao Road Expressway to improve the level of emergency transportation in mountainous areas.

The National Highway 108 auxiliary line is nearly 24 kilometers long and is an important backbone line of the Fangshan District highway network. Affected by the heaviest rainfall this summer, the 108 auxiliary line suffered many damages and traffic was temporarily interrupted. At the restoration and reconstruction site, workers are pouring new retaining walls and laying the foundation for paving new roads.

“The retaining wall here is designed to be 13 meters high and the foundation is 3 meters deep. An additional 3 meters is added to the original retaining wall to ensure that the retaining wall will not collapse when floods occur again. Strengthen the roadbed and road “The protection function of the bed.” Zhu Peixu, Engineering Management Section of Fangshan Highway Branch of the Municipal Transportation Commission, said that 60% of the total project volume has been completed and the asphalt pavement is planned to be completed on November 22.

Dongfang Road is located in the Beigou area of ​​Fangshan and is the lifeline for residents of villages and towns along the route. Since the road that was temporarily cleared was not suitable for buses, the construction unit overcame winter construction difficulties and completed the overall restoration and reconstruction of Dongfang Road on November 15, and buses were once again driving to the people.

Wang Xuefeng, deputy manager of the No. 7 Highway Engineering Office of Beijing Construction Engineering and Maintenance Group, said that Fangdang Road is an important passage connecting Beigou. There are also 8 bus routes around it. If it is not repaired as soon as possible, it will affect the normal travel of surrounding residents. As of November 15, all eight bus routes have been restored to traffic.

According to statistics, heavy rains caused serious damage to highway facilities such as National Highway 108 in Fangshan District. A total of 54 roads need to be restored and reconstructed, with a severely damaged mileage of 238 kilometers, accounting for about a quarter of the total mileage of roads above the county level in Fangshan. There are currently 34 roads. Road restoration and reconstruction work has been completed first.

“The road restoration in Fangshan District involves a total of 34 projects and 54 roads. Currently, 24 projects and 34 roads have been completed. It is expected to be completed before May 31 next year. National Highway 108 is a severely damaged road, with a total length of 99 kilometers. , there are more than 100 major damaged roadbeds. At present, we have completed more than 50% of the repair work.” Wang Yanhui, chief of the Engineering Management Section of the Fangshan Highway Branch of the Municipal Transportation Commission, said.

In accordance with the overall idea of ​​”basic recovery in one year, comprehensive improvement in three years, and long-term high-quality development”, Fangshan District is studying the planning of two new expressways in Beigou and Nangou areas to improve the level of emergency transportation in mountainous areas in the future. “For example, projects such as the construction of the 108 Expressway in Beigou, the construction of Laibao Road Expressway in Nangou, including Jiajin Road, the connecting line between the South and Beigou, have already carried out preliminary research work,” Wang Yanhui said.

(Editors: Chi Mengrui, Bao Congying)

Share so more people can see it

2023-11-20 01:18:00
#Fangshan #completed #restoration #reconstruction #flooddamaged #roads #build #mountain #expressways #future #Peoples #Daily #Online #Beijing #Window

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.