Construction Progress and Traffic Restrictions in Kročehlavy for Future Globus Hypermarket and Residential Development

Last year, according to Globus spokesperson Andrey Turnovská, topsoil was removed and an archaeological survey was carried out on the site where the hypermarket is to stand. A new electrical connection was also built there some time ago.

The mushroom harvest in Kladno can begin. The map will tell you where they grow

The project promises not only a sales area, but also greenery including a park, a watercourse and a retention tank.

Other construction events are now continuing at a brisk pace in the locality. New sidewalks have been built in the neighborhood of the field since spring, and work has progressed on the renovation of the original roundabout in Unhošťská Street. Until the end of the summer, there will therefore be various closures in this part of Kročehlav, and traffic on the adjacent roads is controlled by a shuttle.

Source: Jan Lakomý“The roundabout will grow at the street crossing. At the same time, there will be new connections to the future Globus hypermarket, adjacent buildings and two new streets. Due to the necessary closures, the city is using this opportunity to modify Americká Street, which will have the same look as the current Jaroslava Kocián Street,” said Kladno Mayor Milan Volf (Election for Kladno).

Pedestrian crossings with independent lighting, new bus stops with panel structures, new parking areas for passenger cars and a large amount of greenery are also nearing completion.

The Růžové pole project, which offers great potential, includes future residential construction in the direction of Velké Přítočné next to the shopping center. The change in the zoning plan enabled the creation of a new part of the city, including the expansion of the offer of apartments.


Traffic restrictions in Kročehlavy

Stages 1 and 2 (until August 17 and from August 21 to 31)

– the SOUTH part of the construction and the 2nd stage of the NORTH construction, total closure for car traffic, the operation of public transport buses and vehicles of the integrated rescue system allowed in the direction of American – roundabout – Armenian passing through the building with traffic controlled by shuttle traffic lights
– closure of road I/61 (Unhošťská) in km 9.260 – 9.670, from Velké Přítočn it will not be possible to reach the roundabout Americká x Unhošťská x Arménská and vice versa
– closure of Americká Street in the section from the intersection with Norway to the roundabout Americká x Unhošťská x Arménská
– closure of Arménská street in the section from the intersection with Na Růžovém poli street to the Americká x Unhošťská x Arménská roundabout
– the bypass route for cars up to 6t will be from road I/61 along road II/118 (Milady Horákové)
– the bypass route from District 0 will be through Arménská and Pražská streets
– detour route for transit over 6 tons on roads I/61, D7, D0, D6

Stage 3 (continues from August 18 to 20)

– asphalt laying: total closure for car traffic, traffic of public transport buses and IZS vehicles passing through the construction site will not be possible at this stage
– closure of road I/61 (Unhošťská) at km 9.260 – 9.670, it will not be possible to reach the roundabout Americká x Unhošťská x Arménská from Velké Přítočn and vice versa)
– closure of Americká in the section from the intersection with Norway to the roundabout Americká x Unhošťská x Arménská
– closure of Arménská in the section from the intersection with Na Růžovém poli street to the roundabout Americká x Unhošťská x Arménská
– the bypass route for cars up to 6t will be from road I/61 along road II/118 (Milady Horákové) and then along Milady Horákové street back to road I/61 with a variant from road I/61 along Vodárenská
– the bypass route from District 0 will be through Arménská and Pražská streets
– detour route for transit over 6 tons will be possible along roads I/61, D7, D0, D6