29/10/2024 17:35
(PLO) – In early November 2024, the Land Assets Development Board and Project Management of Cai Rang area (Can Tho City) will approve the winning bid results and sign the reinstatement construction contract By the end of 2024, to discuss. delivery of land.
29 October, news from the People’s Committee Can To City he said it was related to shift work The landfill blocks the highway Can Tho – Ca Mau, Cai Rang district is expected to hand over the property to the investor on December 31.
In particular, on October 15, the Cai Rang District Land Fund Development Board and Project Management Board posted application documents on the National Application System and closed applications on October 24. In early November 2024, the unit will approve the winning bid results and sign a construction contract to move the amount of waste. Estimated build time is 45 days.
Also according to the People’s Committee Can To Cityduring the construction process, temporary fencing will be installed around the landfill and temporary roads and service roads will be installed. In addition, take steps to treat odors, control insects with microbial products and have a plan for collecting waste sludge and leachate.
For the waste transfer process, it will be divided into 4 layers, each layer will be dug in turn and transported to the waste disposal area. Waste is moved from the site’s clean-up area to adjacent areas within the existing landfill.
The Northeast – South Expressway, period 2021 – 2025, Can Tho – Ca Mau section is divided into two component projects, including: Can Tho – Hau Giang section and Hau Giang – Ca Mau section. There, the section goes through the area Can To City 0.6km long, total link road length is more than 9.2km.
At the end of August 2023, Can To City It was reported that 100% of the site was given to the building unit. However, during the conveyance process, a landfill was found crossing the 7km link section of the expressway, the section from IC2 intersection to National Highway 1A.
After finding out about the incident, in January 2024, the Town’s People’s Committee had a meeting to resolve it. This is the People’s Committee Can To City Assign the Department of Natural Resources and the Environment to evaluate the results of waste classification. At the same time, evaluate the resettlement plan and estimate the cost to be the basis for the Cai Rang District People’s Committee to approve the resettlement plan.
By early March 2024, the People’s Committee Can To City They issued an Official Release asking the Department of Natural Resources and Environment to urgently consider and resolve according to their authority the recommendations of the Cai Rang District People’s Committee related to this landfill and report the results to the Town People’s Committee.
According to the estimates of authorities Can To CityLandfill No. has an area of approximately 4.3 hectares. 8 and contains approximately 162,540 tons of waste. In which the area of overlap between the highway and this landfill is more than 1.7 hectares, the amount of waste in the overlap exceeds 67,109 tons.