According to the electronic communication portal of Hanoi city, on Vinh Tuy bridge – phase 2, people and vehicles participating in traffic go one way in the direction from Hai Ba Trung to Long Bien, and are divided into lanes in the direction: 3 lanes motor vehicles – lanes next to the median strip with a width of 3.75m/each lane, maximum operating speed of 60km/h.
1 mixed lane (motorcycles and rudimentary vehicles) – the lane next to the right handrail of the bridge with a width of 4.8m, maximum operating speed of 40km/h.
Dividing motor vehicle lanes with mixed traffic lanes by means of a rigid divider and a system of warning signs to separate lanes on a long gate rack.
People and vehicles participating in traffic go one way from Hai Ba Trung to Vinh Tuy Bridge, phase 2, through 3 branches to the bridge.
Specifically, going from Nguyen Khoai dyke road in the direction from Thanh Tri bridge to Vinh Tuy bridge, turn right and enter CV1B bridge branch with a lane width of 6m.
Follow Nguyen Khoai dike road, direction from Chuong Duong bridge to Thanh Tri bridge, if you want to go to Long Bien, turn right along CV1A branch to Vinh Tuy bridge phase 2 with a lane width of 7m.
Going from Minh Khai street and Ring 2 overhead viaduct, if you want to go to Long Bien, you will go straight to Vinh Tuy bridge – phase 2.
With the old Vinh Tuy bridge (Vinh Tuy bridge phase 1), people and vehicles participating in traffic go one way in the direction from Long Bien to Hai Ba Trung and are divided into lanes in the direction:
4 lanes for motor vehicles – the lane next to the median strip with a lane width of 3m, maximum operating speed of 40km/h.
1 mixed lane (motorcycles and rudimentary vehicles) – the lane next to the right handrail of the bridge with a lane width of 2.7m, a maximum operating speed of 30km/h.
Dividing motor vehicle lanes with mixed lanes with painted lanes and a system of lane markings, warning signs “The route is completing the infrastructure system to ensure traffic” on the long gate.
The road system on both sides of Vinh Tuy bridge – Dam Quang Trung street (Long Bien district) organizes traffic for people and vehicles participating in traffic going one way (in the same direction as vehicles passing through Vinh Tuy bridge) on the road. Dam Quang Trung – the passage from Co Linh to Bat Block and vice versa.
Time to implement channelization from August 30, right after the opening ceremony of Vinh Tuy bridge phase 2.