Temelín energy plant spokesperson Marek Sviták informed the information that the primary Temelín unit began supplying electrical energy to the transmission system at fifty % reactor capability.
It ought to attain full efficiency inside just a few days. Through the warm-up, a number of different exams await the vitality engineers.
“That is, for instance, exams at eighty % energy, once we decide the balanced distribution of the ability of the reactor. We will even monitor different tools, particularly the turbine, the place a whole lot of millimeters are sure throughout operation,” stated Jan Kruml, director of the Temelín Nuclear Energy Plant.
The modernization of safety techniques has begun in Temelín
Financial
Through the shutdown, vitality staff changed 48 out of 163 gasoline units, inspected the protection techniques, the turbine, the generator and carried out 66 stock actions. A few thousand folks have been concerned within the work along with the suppliers.
“Presently, the manpower capabilities of our workers and suppliers concerned within the shutdown have moved to Dukovan, the place the deliberate shutdown of the second unit is going down,” stated Bohdan Zronek, a member of CEZ board of administrators and director of the nuclear vitality division.
The subsequent shutdown awaits Temelín within the autumn, when the second unit will bear inspection and new gasoline.
Each the Koreans and the French submitted bids for the development of nuclear blocks