The Largest reform in the history of the Stadium since it opened in 1959 has been approached in phasessince November of last year, with the premise of continuing making it easier for its subscribers to practice sports in a unique environment What is the stadium like?
New entrance and cafeteria
The first stage of the work has already been completed with a new entrance, a more integrated, accessible and useful cafeteria terrace. In addition, an area of Shared work and the indoor tennis court where subscribers already enjoy taking their best shots and emulating Rafa Nadal, Carlos Alcaraz or Roger Federer.
Definition of the new complex
The works for dispose of Estadio Berria in January 2024 now face the turning point of the second phase that will end up defining the renovated sports complex. The new building, attached to the ratchet, has been consolidated
The less showy and fundamental part of concrete, structure, roof and new slabs has come to an end.
The part begins in which the new rooms begin to be erected and spaces begin to be generated where, not long after, the Stadium subscribers will be enjoying group activities.
New activity rooms
The access from the main building is already outlined with the stairs that will equalize the height with that of the rooms. In this plant, the high intensity interval training slots (HIT) and the future spinning room in stands. The limits of the room are already intuited with the future windows, and the pedestrian access from the walkway over the ratchet stands.
Going up the stairs they see the activity rooms (healthy back, yoga, pilates, tai chi, among other). In these spaces it has been wanted enhance the contribution of natural light by installing large windows that make it easy.
At the end of the corridor is prepared the area where the covered and heated walkway will connect the activities building with the main.
Second floor
Through a hole in that wall you access the second floor of the existing building, where the multifunctional room will be which will house the most massive activities of the Stadium. With endowment of stretching area in the old engine room.
The roof is now just waiting for the tape and the air conditioning machines and, of course, the solar panels that will help the complex to be as respectful as possible with the environment.
This daily work has the with the objective of ensuring the best possible experience for Stadium subscribers and the commitment that for the next sports campaign, which will begin in autumn, these new spaces can be seen and tested and in January 2024 have everything ready and ready at the beginning of the renewed journey.